Seattle
Cannot Impose Additional Safety Standards for Hazardous Pipeline
Terra
Bowling, 3L, University of Mississippi School of Law
In February, the United States Court of Appeals for the Ninth Circuit
ruled that the City of Seattles attempts to impose additional
safety requirements on Olympic Pipe Line Company (Olympic Pipe Line)
were preempted by the federal Pipeline Safety Act (PSA).
Background
The litigation involved a lateral delivery line, called the Seattle
Lateral, that Olympic Pipe Line has operated under a franchise
agreement with the city since 1966. The Seattle Lateral runs near elementary
schools and a residential neighborhood, underneath Interstate 5, and
next to electricity transmission lines. Seattle sought to regulate the
pipeline after a segment exploded in Bellingham, Washington, killing
three people and causing extensive environmental damage.
Olympic Pipe Lines contract with the city came up for renewal
soon after the Bellingham explosion. Before the city would consider
agreeing to a new franchise agreement, it requested Olympic respond
to thirty-three of its safety concerns. Among those items was a request
that the company perform a hydrostatic test of the pipeline. The Office
of Pipeline Safety of the Department of Transportation (DOT) notified
Seattle that the tests of the Seattle Lateral were not necessary because
the pipeline met federal regulatory standards. Olympic then filed an
action in district court against Seattle to stop the city from ordering
Olympic to shut down operations.
The district court ruled that the city was preempted from regulating
the safety and inspection of the Seattle Lateral by the PSA. Seattle
appealed, arguing that the PSA does not entirely preempt the city from
regulation. The city also asserted that, even if the PSA does preempt
the citys actions, Olympic waived its right to argue preemption
when it entered into the franchise and indemnity agreements with the
city. Finally, the city asserted that those agreements should be enforced
as a matter of public policy.
Preemption
The Ninth Circuit first considered whether the PSA preempted Seattles
attempt to impose safety standards on a hazardous liquid pipeline. The
court recognized that the Supremacy Clause of Article VI of the United
States Constitution grants Congress the power to preempt state or local
law. The court examined the statutory text of the PSA to determine whether
it expressly prohibited regulation by local authorities or if it could
be reasonably inferred that Congress did not leave room for local regulation.
The PSA has different rules for the regulation of interstate and intrastate
pipelines. States and local authorities may exercise limited regulatory
authority over interstate pipelines through a safety agreement or as
an agent of the DOT, but generally they may not enact safety standards.1
After being certified by DOT, a state authority may regulate intrastate
pipelines if its standards are consistent with federal pipeline safety
standards.2 The court found that regardless of whether
the Seattle Lateral was considered an interstate or intrastate pipeline,
the city needed to receive authorization from the DOT to regulate the
pipeline.
The state of Washington had received authority from DOT to participate
in the pipeline safety program for intrastate lines after the Bellingham
incident. The court, however, found that Seattle had neither sought
nor been delegated authority to regulate the pipeline. The court concluded
that the PSA expressly preempts the citys attempt to impose safety
regulations on the Seattle Lateral.
The court indicated that the city could impose requirements on Olympic
Pipe Line, such as safety tests or the purchase of liability insurance,
if Seattle is acting as a municipal proprietor rather than as a regulator.
The court found, however, that Seattles interest was not that
of a private market participant that owns a pipeline, but that of a
regulator seeking to protect the public health and safety. As such,
Seattle could not impose safety standards under the market proprietor
exception.
Additional
Claims
Seattle also claimed that the company had waived its right to use the
preemption argument when it entered the franchise and indemnity agreements
with the city. The court rejected this argument, holding that preemption
is a federal power and not a right a private party can waive.
The court rejected Seattles argument that a court ruling that
the citys safety provisions are unenforceable will encourage other
companies to enter into contracts they do not intend to honor. The court
noted that the citys policy concern is outweighed by the federal
need to maintain uniformity in the establishment and enforcement of
hazardous liquid pipeline safety regulations.
Conclusion
The Ninth Circuit affirmed the ruling of the district court that Seattles
attempts to impose additional safety requirements on a hazardous liquid
pipeline were preempted by the PSA.
Endnotes
1. 49 U.S.C. §§ 60104(c), 60106(a), 60117(c).
2. Id. § 60104(c).
|
|