|
FERC
Has Authority to Require Invasive Species Monitoring Plans
Rhinelander
Paper Co. v. FERC, 405 F.3d 1 (D.C. Cir. 2005).
Stephen
Janasie, 3L, Chicago-Kent College of Law
The D.C. Circuit
Court of Appeals recently affirmed the Federal Energy Regulatory Commissions
(FERC) decision to delay modification of a hydroelectric projects
license boundaries and to require, as a provision of the renewal license,
the development of an invasive species monitoring plan. The court found
both actions a reasonable exercise of FERCs authority under the
Federal Power Act.
Background
The Rhinelander Paper Company (Rhinelander) operates a hydroelectric
plant on the Wisconsin River in Oneida County, Wisconsin. On June 26,
1998, the company filed an application to renew its license with FERC
for the 2.12 megawatt project. Under the previous license, the project
encompassed approximately 2,478.5 acres of land. The modification would
have removed privately owned land from the project boundaries and reduced
the size of the project to approximately 292.5 acres.
On August 20, 2003, FERC renewed Rhinelanders license under the
Federal Power Act, but did not accept the companys modification.
In addition, FERC inserted two important provisions in the renewal license.
First, FERC required that the project maintain its historical boundaries
pending the preparation of a land management plan. Second, FERC required
that Rhinelander develop and implement a plan to monitor invasive plant
species at the project.
The U.S. Fish & Wildlife Service (FWS) was the primary impetus behind
the addition of these two provisions. The FWS recommended maintaining
the historical boundaries of the project until Rhinelander provided
a clearer identification of the land to be removed from the project.
The FWS also requested that the license renewal require Rhinelander
to cooperate with state and federal agencies to monitor and control
the spread of highly invasive and exotic plant species, despite the
fact that there was no evidence of the presence of such species at the
project.
Rhinelander requested a rehearing on the Directors decision, which
was denied on February 18, 2004. In its denial, FERC admitted that the
land slated for removal may not be necessary, but also stated that more
information was needed before a decision could be made. Also, FERC stated
that the plant monitoring provision was appropriate since section 10(j)(1)
of the Federal Power Act requires FERC to include in each hydroelectric
license conditions to adequately and equitably protect, mitigate
damages to, and enhance, fish and wildlife (including related spawning
grounds and habitat), based on recommendations from federal and
state resource agencies.1 Rhinelander then brought
the decision before the D.C. Circuit Court of Appeals for review.
Boundary
Modification
In reviewing a FERC licensing decision, the courts are held to the commonly
employed arbitrary and capricious standard.2 In other words, a court must determine if the Commissions decision
was reasonable and within the bounds of the powers granted to the agency
by Congress. In this case, the D.C. Court of Appeals determined that
the Commission had made a proper decision with regard to both issues.
In regards to the first issue, FERC based its decision on section 10(j)(1)
of the Federal Power Act, which states in part that:
the project adopted,
including the maps, plans, and specifications, shall be such as in the
judgment of the Commission will be best adapted to a comprehensive plan
for improving or developing a waterway or waterways for the use or benefit
of interstate or foreign commerce, for the improvement and utilization
of water-power development, for the adequate protection, mitigation,
and enhancement of fish and wildlife (including related spawning grounds
and habitat), and for other beneficial public uses, including irrigation,
flood control, water supply, and recreational and other purposes.3
The Commission has
construed this portion of the Act as imposing a statutory obligation
upon both the Commission and the licensee to protect the shoreline and
aquatic resources within the project area through the use of a buffer
zone. While a modification of the project area in this case may have
been acceptable, FERC contended that Rhinelander had not provided sufficient
maps and other specific information about the lands for the Commission
to make an informed decision concerning boundary modification. The D.C.
Court of Appeals found FERCs basis for this decision entirely
reasonable.
Invasive
Species Monitoring Plan
In regards to the second issue, the D.C. Court of Appeals also held
that the Commissions decision was not arbitrary and capricious.
As stated earlier, FERC based this decision on section 10(j)(1) of the
Federal Power Act, which requires licenses to protect, mitigate and
enhance wildlife in the project area. The court used the classic Chevron
analysis: determining whether Congress has spoken directly on the point
at issue, and if not, whether the agency in question has made a permissible
reading of the statute.4 The D.C. Court of Appeals
held that FERCs reading of section 10(j)(1) was permissible. Specifically,
the court referred back to Rhinelanders own admissions at oral
arguments that a hydroelectric project like the one at issue in this
case obviously has an affect upon fish and wildlife within a river system,
and that the project has the potential to spread the invasive species
at issue through the contribution of the seeds of these plants to the
flow of the river. While the court acknowledged that prior cases had
held that provisions which required project operators to work with agencies
to control the spread of these plant species were premature, the court
pointed out that this license merely required the operator to implement
a plan for cooperative monitoring efforts. Thus, FERCs decision
was an acceptable interpretation of the statute at issue, and was not
in conflict with previous license decisions.
Conclusion
The spread of invasive species like purple loosestrife and Eurasian
water-milfoil have become an issue of national import. The courts
decision in this case is an important step in fighting the problems
caused by these invasive species, as it has read into the Federal Power
Act a federal statutory basis for FERC to impose monitoring obligations
upon hydroelectric projects. These projects are acknowledged as a significant
cause of the spread of these species, and this decision represents one
method by which to combat the problem. If similar obligations can be
read into the habitat conservation provisions of other agencys
statutes, perhaps the spread of invasive species through methods such
as ship ballast water can be more adequately addressed in the future.
Endnotes
1. Rhinelander Paper Co. v. FERC, 405 F.3d 1,4
(D.C. Cir. 2005).
2. Alabama Rivers Alliance v. FERC, 325 F.3d
290, 296 (D.C. Cir. 2003), citing North Carolina v. FERC, 112
F.3d 1175, 1189 (D.C. Cir. 1997).
3. 16 U.S.C. § 803(a)(1).
4. Chevron U.S.A., Inc. v. Natural Resources Defense
Council, Inc., 467 U.S. 837 (1984).
|
|