|
Dock Extension Delayed because of Inadequate EIS Ocean Advocates v. U.S. Army Corps of Engineers, 361 F.3d 1108 (9th Cir. 2004). Stephanie Showalter, J.D., M.S.E.L. In March, the Ninth Circuit Court of Appeals delayed the planned expansion of an oil refinery dock in Washington State until the U.S. Army Corps of Engineers (Corps) prepares a full Environmental Impact Statement (EIS) and reassesses the permit under the Magnuson Amendment. This is a case of first impression with respect to the Magnuson Amendment. Background In 1992, BP applied
for a permit from the Corps to build the northern platform and return
to the refinerys original plans for separate docks for loading
and unloading. During the public comment period, the U.S. Fish and Wildlife
Service (FWS) expressed concern that the increase in tanker traffic
as a result of the expansion would increase the possibility of a major
oil spill. The Lummi Indian Nation and the Nooksack Indian Tribe expressed
similar misgivings. On March 1, 1996,
the Corps approved BPs permit application, finding that the construction
of the northern platform would not result in adverse cumulative impacts
to fish and wildlife in the Cherry Point area. The Corps claimed that
the dock expansion would reduce the risk of oil spill because of a decrease
in tanker wait time and the installation of oil spill containment booms
around the new platform.1 The Corps determined that
the expansion would not significantly affect the quality of the
human environment and issued a Finding of No Significant Impact
(FONSI) under the National Environmental Policy Act (NEPA) thereby excusing
the agency from preparing an EIS.2 In 1997, Ocean Advocates
contacted the Corps requesting a more thorough analysis of the cumulative
impacts of the dock expansion on vessel traffic and whether the permit
violated the Magnuson Amendment3 which regulates permits
for oil transport terminals in Puget Sound. The Corps denied both requests.
Ocean Advocates submitted a second request for reconsideration in 1999. In 2000, the Corps granted BP a one-year extension to its 1996 permit to complete construction, finding that the dock extension did not violate the Magnuson Amendment because the extension would not increase the facilitys capacity to offload crude oil. The Corps again determined that an EIS was unnecessary. The northern platform is currently operational. The
Lawsuit Preliminary
Matters BP also argued that OAs action was barred on the basis of laches. Laches is disfavored in environmental cases, but it is an affirmative defense if a defendant can show that the plaintiff lacked diligence in pursuing her claim and that lack of diligence resulted in prejudice to the defendant. The Ninth Circuit held that laches does not bar OAs action, due to OAs diligent pursuit of its claim from the Corps issuance of the first permit in 1996. NEPA The Ninth Circuit
was not persuaded that the Corps took a hard look at the
environmental impacts of the proposed dock expansion. The court held
that the Corps failed, in both 1996 and 2000, to provide any reason
why an EIS was unnecessary.8 The Corps simply
stated that the project would not have a significant impact on the quality
of the human environment. Such a statement alone, without supporting
reasons, is insufficient to satisfy the NEPA requirements. The court found
that an EIS is required for the dock expansion. First, in its communications
with the Corps, the court found that OA raised a substantial question
regarding whether the northern platform might cause significant degradation
of the environment. In addition, the court determined that the Corps
failed to adequately examine the cumulative effects of multiple projects
in the Cherry Point area as required under 40 C.F.R. § 1508.27(b)(7).
Finally, an agency must prepare an EIS when the effects of the project
are highly uncertain.9 The court determined that the
Corps did not have the necessary data to determine whether tanker traffic
would increase as a result of the expansion and therefore should have
prepared an EIS.
BP claimed that
the northern platform cannot and would not be used to unload crude oil
and, therefore, the expansion did not increase the amount of crude oil
which could be handled. However, the court held that the phrase any
such facility refers to more than the northern dock expansion
itself. The relevant question is whether the permit enabled BP to increase
the capacity of its entire Cherry Point Marine Terminal to handle more
crude oil. The Ninth Circuit
could not answer this question because it was not clear from the record
whether the terms of BPs permit limited BPs ability to handle
crude oil at the northern platform. While BP argued that the platform
was physically incapable of handling crude oil, BPs permit does
not clearly prohibit BP from modifying the new platform to handle crude
oil. If the permit allows BP to modify the platform, then the Corps
may have increased the capacity of the Cherry Point terminal to handle
crude oil in violation of the Magnuson Amendment.
If the answer to
either of these questions is yes, then the permit violates the Magnuson
Amendment and is invalid. Stated another way, BP and the Corps must
prove on remand that the new platform cannot handle crude oil without
additional permits from the Corps. The Ninth Circuit also directed the district court to investigate whether the permit allowed BP to increase the berthing capacity of the Cherry Point Terminal. If so, the increased berthing capacity could potentially increase the capacity of the terminal to handle crude oil, again in violation of the Magnuson Amendment. Conclusion Endnotes . |
|||||||||||||
|
Phone (662) 915-7775 • Fax (662) 915-5267 • 256 Kinard Hall, Wing E, University, MS 38677-1848
Sitemap • Please report any broken links/problems to the Webmaster |
|||||||||||||