![]() |
||||||||||||||
![]() |
||||||||||||||
![]() |
||||||||||||||
|
Construction of Navy Landing Field Delayed Washington County, N.C. v. U.S. Dept. of the Navy, 2004 U.S. Dist. LEXIS 8733 (E.D.N.C. April 19, 2004). Stephanie Showalter, J.D., M.S.E.L. In April, the U.S. District Court for the Eastern District of North Carolina enjoined the U.S. Navy from taking further action associated with the construction of a landing field near the Pocosin Lakes National Wildlife Refuge (Pocosin NWR) pending a decision on the merits in a lawsuit filed by the Southern Environmental Law Center. Background On January 9, 2004,
the Southern Environmental Law Center (SELC) filed suit on behalf of
the National Audubon Society, North Carolina Wildlife Federation, and
Defenders of Wildlife challenging the Navys plan to construct
a new OLF at Site C. SELC claims that the Navy failed to comply with
the National Environmental Policy Act (NEPA), the Coastal Zone Management
Act, and the North Carolina Coastal Area Management Plan. In February,
SELC filed for a preliminary injunction to prevent the Navy from moving
ahead with its construction plans until the court made a determination
on the merits of the case. A preliminary injunction
is not the final determination of a case, but rather a temporary remedy
to preserve the status quo until a final ruling can be made by the court.
Usually, to obtain a preliminary injunction, the moving party must establish:
(1) a substantial likelihood of success on the merits; (2) irreparable
injury to the [moving party] if the injunction is denied; (3) the threatened
injury to the [moving party] outweighs the injury to the other party;
(4) the injunction is not adverse to the public interest.3
No one factor is determinative. In the Fourth Circuit, however, courts employ a hardship balancing test that balances the likelihood of harm to the plaintiff against the likelihood of harm to the defendant.4 If the balance of harms weighs in the plaintiffs favor, the plaintiff need not demonstrate a likelihood of success.5 The plaintiff simply needs to show that her claims raise serious questions. Balance
of Harms The likelihood of harm to the Navy, according to the district court, is slight. The Navy is still in the preliminary planning stage of this project and has yet to purchase land or secure contractor bids. Furthermore, the court was not persuaded by the Navys primary argument that a construction delay would irreparably harm the ability of the Navy to conduct operations. Even without a delay, the OLF would not be operational until 2007 and even the Navy admitted in its Final Environmental Impact Statement that an OLF is not required to support the homebasing alternatives at NAS Oceana.6 Likelihood
of Success Conclusion Endnotes . |
|||||||||||||
|
Phone (662) 915-7775 • Fax (662) 915-5267 • 256 Kinard Hall, Wing E, University, MS 38677-1848
Sitemap • Please report any broken links/problems to the Webmaster |