Formal
Cumulative Impacts Analysis Not Required Under Alaska Law
Greenpeace, Inc. v. State of
Alaska, 79 P. 3d 591 (Alaska 2003).
Shannon
McGhee, 2L
The Supreme Court of Alaska recently addressed
whether Alaska requires a NEPA-like or whole-project
approach to cumulative impacts analysis when projects are reviewed
for consistency with the States coastal management plan.
Background
In 1995, British Petroleum Exploration (BP) purchased four oil
and gas leases to develop Alaskas first offshore oil facility
and subsea oil pipeline in the Beaufort Sea near Prudhoe Bay.
BPs plans, known as the Northstar Project, required several
federal and state permits. Any project impacting Alaskas
coastal areas and requiring multiple permits must undergo a
comprehensive review to determine its consistency with Alaskas
Coastal Management Program (ACMP). The Alaska Division of Government
Coordination (DGC) administers the review and is responsible
for issuing the consistency determination. Due to the nature
of the Northstar Project, the United States Army Corps of Engineers
was also required to review the project under the National Environmental
Policy Act (NEPA) and prepare an Environmental Impact Statement.
In an effort to expedite the review process, the DGC and Army
Corps of Engineers (Corps) coordinated their reviews.
During the review process, public comment was sought by DGC
and the Corps. Greenpeace responded with extensive comments.
DGC found the Northstar Project consistent with ACMPs
standards in a Proposed Consistency Determination in early 1999.
Greenpeace, unhappy with the consistency determination, asked
the Alaska Coastal Policy Council to review whether Greenpeaces
comments were fairly considered in the proposed consistency
determination. The Council sustained the proposed consistency
determination and the DGC issued a Final Consistency Determination
on February 4, 1999.
Greenpeace appealed the Final Consistency Determination
to the Alaska Superior Court. The superior court affirmed DGCs
decision and Greenpeace appealed to the Supreme Court of Alaska.
Greenpeace alleged as a matter of law that DGC failed to apply
the proper cumulative impacts analysis and phasing procedural
requirements mandated under ACMP. On appeal, the Supreme Court
ruled Alaska law did not require DGC to perform a NEPA-like
cumulative impact analysis and that Northstar was not a phased
project.
Cumulative
Impacts
Greenpeace argued that the proper standard for a cumulative
impacts analysis under the ACMP should be defined as the
impact on the environment which results from the incremental
impacts of the action when added to other past, present, and
reasonably foreseeable future actions.1 Greenpeace supported its argument by claiming the federal governments
Final Environmental Impact Statement implicitly endorsed a NEPA-like
definition by describing the ACMPs standards as encompassing
a general balancing process taking account of public need,
alternatives, and cumulative effects . . .2 Greenpeace also claimed Alaska law defines a use of direct
and significant impact in a way that considers the cumulative
effects of a coastal project.3
The DGC, on the other hand, asserted Alaska
law and cases support a whole-project analysis approach
to the meaning of cumulative impacts. This whole-project analysis
would require the DGC to evaluate the combined impacts of all
aspects of the project under review, but not require the DGC
to examine the project in light of hypothetical or proposed
future development in the region.4
The Court agreed with the DGC that a NEPA-like
cumulative impacts analysis is not warranted by the ACMP because
the NEPA review process is already part of the consistency review
for projects like Northstar. The placement of structures
and the discharge of dredged or fill material into coastal water
must, at a minimum, comply with the standards contained in Parts
320-323, 33 C.F.R. 47, a federal regulation under NEPA
requiring a formal cumulative impacts analysis.5
This provision ensures that proposed projects requiring federal
permits will achieve the minimal level of compliance with Alaskan
law upon approval of a federal permit. It does not, as Greenpeace
suggests, add an additional layer of cumulative impacts analysis.
This statute does not require DGC to conduct an independent
review. While the DGC must review and consider any cumulative
impact analysis prepared by a federal agency, the DGC remains
free to accept or reject the federal analysis.6
The Supreme Court reasoned that a separate level of review is
unnecessary because of the availability of a federally prepared
cumulative impacts analysis.
The Court also noted that ACMP standards require
the DGC to consider a projects known and predictable effects
during the consistency review, such as adjacent uses and even
subsequent adjacent uses. The Court rationalized a whole-project
analysis, as suggested by the DGC, as more compatible
with these standards because it takes into account all
aspects of a project, considered as a whole and its existing
development context but does not require the DGC to speculate
about unknown and unpredictable future events as does a NEPA-defined
cumulative impact analysis.7
Greenpeace also argued that the federal Coastal
Zone Management Act (CZMA), as well as the DGC handbooks, promoted
a NEPA-like cumulative impacts analysis for ACMP consistency
reviews. No provision in the CZMA or its regulations mandates
Alaska adopt a NEPA-like cumulative impact analysis. The Court
also rejected similar arguments that the DGC handbooks and policies
required a NEPA-defined cumulative impacts analysis, stating
that at the most these materials simply encourage coastal
districts to develop cumulative impact analysis guidelines .
. .8
Finally, Greenpeace contended that even under
DGCs whole project cumulative impacts analysis,
DGC still failed to consider the incremental contribution
of Northstar, in the context of past, present and reasonably
foreseeable actions, rendering the DGC decision arbitrary
and capricious.9 Therefore, the DGCs
consistency determination could only fail because the agency
failed to make a reasonable decision. Agency decisions are generally
reviewed under the hard look standard - examining
whether the agency took a hard look at the issues.
The failure to comply with the hard look standard
is a separate issue which was not raised by Greenpeace on appeal.
Greenpeace argued that the DGC failed to comply with mandatory
procedures. Because a NEPA-like cumulative impacts analysis
is not required, the DGCs final consistency determination
complied with mandatory ACMP procedures. Greenpeace waited to
raise the issue of failure to comply with the hard look
standard until it filed its reply briefs with the court. The
Supreme Court held that Greenpeace waived its right to argue
this issue by failing to raise the issue on appeal.
Phasing
The second procedural issue was whether DGC improperly phased
the Northstar Project by prematurely issuing permits and approving
major aspects of the projects future developments
without sufficient information to make a reasoned ACMP consistency
determination. The Court succinctly concluded that the Northstar
project was not phased and that the consistency review encompassed
the project in its entirety.
Conclusion
The Supreme Court of Alaska determined Alaska law did not require
DCG to produce NEPA-like cumulative impact analysis during their
ACMP consistency review of the Northstar Project and affirmed
DCGs final consistency determination.
Endnotes:
1. Greenpeace, Inc. v. State, 79 P. 3d 591,
593 (Alaska 2003) (citing 40 C.F.R. § 1508.7 (2002)).
2. Id. at 594.
3. Id. (citing Alaska Stat § 46.40.210
(1995)).
4. Id.
5. Alaska Admin. Code tit. 6, § 80.040
(2000).
6. Greenpeace, 79 P. 3d at 595, n 20.
7. Id. at 596.
8. Id. at 597.
9. Id. at 598.