Gradual
Takings Claim Not Barred by Statute of Limitations
Banks
v. U.S., 314 F.3d 1304 (Fed. Cir. 2003).
Jason
Savarese, 2L
The Federal
Circuit recently addressed the time limits for filing a gradual
takings lawsuit, in which a landowner argues that his property
has been taken by government action over the course of several
years.
Background
A group of landowners with acreage running along four miles
of Lake Michigan sued the U.S. claiming marina jetties installed
by the Army Corps of Engineers (the Corps) were causing a gradual,
yet steady erosion of their properties. Although the shorelines
of the Great Lakes naturally erode, the erosion had been accelerated
over the years by the construction of the harbor jetties, built
by the Corps in Lake Michigans St. Joseph Harbor around
1903. The jetties were upgraded using sandtight steel sheet
piling from 1950 through 1989. These improvements doubled the
annual, natural erosion rate of Lake Michigans littoral
land abutting the jetties from one to two feet per year.
Because of the increased erosion surrounding St. Joseph Harbor,
the Corps developed a sand mitigation plan pursuant to the Rivers
and Harbors Act.1 For over fifteen years the
Corps attempted to mitigate the erosion by nourishing and replenishing
the beaches with fine sand. In 1986, the Corps switched to coarser
materials with a longer retention time on the beach.
The Lawsuit
The landowners sued the United States in July of 1999, charging
the Corps with restricting the natural flow of sand and river
sediment to their properties, causing a slow, yet unceasing
taking of their littoral land without just compensation. The
owners claimed these jetties and some dredging projects had
permanently taken away sand needed to replenish the naturally
eroding shorelines along Lake Michigan.
The Corps moved to dismiss for lack of jurisdiction, arguing
that the takings occurred more than six years before the Plaintiffs
filed suit, and thus the claim was barred by the six-year statute
of limitations. Claims against the government must be filed
within six years after such a claim first accrues.2
The landowners argued that their gradual takings claims
were unclear until the end of the 1990s, when, through the compilation
of three Corps technical reports, they learned that the visible
erosion of their littoral land was both permanent and irreversible.
The Court of Federal Claims determined that the statute of limitations
began to run in 1989, the year the Corps completed the steel
sheet piling upgrades. Because the landowners waited to file
their claims until July 9, 1999, ten years later, the court
ruled their claims time-barred and dismissed the lawsuit. The
landowners appealed.
Stabilization
Doctrine
In this situation, the erosion of the landowners properties
was not sudden nor obvious. Rather, the taking occurred over
the course of a century. A gradual physical takings claim accrues
when the condition stabilizes, or when the result of the government
action is demonstrated to be a permanent taking. It is important
to note that a claim does not accrue simply because the process
causing the gradual taking ceases nor does it accrue when the
full extent of damage can be determined. The law requires the
condition to stabilize so that a more accurate damage assessment
can be made. This also ensures that the landowner receives notice
of the permanent nature of the condition. Before a claim can
accrue, the situation must stabilize to the point that the consequences
of [the government action] have so manifested themselves that
a final account may be struck.3 Basically,
under the stabilization doctrine, a claim stabilizes when
the permanent nature of the taking is evident.4
The Corps
Technical Reports
In the present case, the main question was whether the landowners
were justifiably uncertain about the impacts of the Corps
mitigation efforts on the permanence of the damage to their
land no earlier than 1999. The Court held that the vast uncertainty
caused by the Corps twenty-three year period of mitigation,
which appeared successful, stayed the accrual of the takings
claims until the release of the Corps three technical
reports revealed the permanent and irreversible nature of the
erosion. Technical reports on the St. Joseph mitigation endeavor
were issued by the Corps in 1996, 1997, and 1999. The June 1996
report expressed uncertainty about the impact of the beach nourishment
program, but stated that mitigation might provide partial protection
against erosion. The 1997 Technical Report described the erosion
as irreversible, but also discussed a favorable change in the
amount of sand eroding in the area. The court held that these
two reports would have confused landowners as to whether they
were suffering a permanent and irreversible taking or if the
mitigation measures were succeeding. It was not until the January
1999 Report that the Corps stressed the irreversible and possibly
permanent nature of the erosion. The permanent nature of the
taking could not have been known by the landowners until the
Reports were issued. The court ruled that accrual of the landowners
claims began when the 1996, 1997, and 1999 reports were issued.
Conclusion
The landowners are not barred by the statute of limitations
since their claims were filed within six years of the time the
claim accrued. The case was remanded for further proceedings
before the Court of Federal Claims.
ENDNOTES
1. River and Harbor Act of 1968, Pub. L. No.
90-483, 82 Stat. 731, 735 (1970). Section 111 of the RHA gives
the Secretary of the Army the power to investigate, study,
and construct projects for the prevention or mitigation of shore
damages attributable to Federal navigation works.
2. 28 U.S.C. § 2501 (2003).
3. United States v. Dickinson, 331 U.S. 745,
749 (1947).
4. Banks v. United States, 314 F.3d 1304, 1309
(Fed. Cir. 2003).
Report any problems or broken
links to Webmaster
University
of Mississippi
|