Sea Grant Law Center
 

Groundfish Management Proves Daunting to Court, Fishers


Conservation Law Foundation v. Evans, 211 F. Supp. 2d 55 (D. D.C. 2002).

Kristen M. Fletcher, J.D., LL.M.

Sarah Elizabeth Gardner, J.D.


Since the passage of the Sustainable Fisheries Act1 in 1996 and dwindling fish stocks across the nation, litigation over the management of U.S. fisheries has increased dramatically. In the spring of 2002, Judge Gladys Kessler of the U.S. District Court for the District of Columbia issued a decision that greatly reduced the fishing effort in the New England groundfish fishery. Since the decision, negotiations between the parties and doubts regarding the science of groundfish management have resulted in a daunting challenge to stabilize the fish stocks and the fishing industry.


Managing Groundfish

The New England Fishery Management Council is mandated by the Magnuson-Stevens Act to develop a fishery management plan (FMP) for the groundfish fishery which had seen severe depletion in the last two decades. By law, the Council is required to prevent overfishing and rebuild depleted fish populations, and to report, assess, and minimize bycatch.2 Amendment 9 to the FMP revised the maximum annual fishing mortality rates for 12 depleted groundfish species.3

 A coalition of environmental groups, led by the Conservation Law Foundation, alleged that by approving Amendment 9, the Secretary of Commerce and National Marine Fisheries Service (NMFS) failed to minimize bycatch and failed to comply with the overfishing and fishery rebuilding provisions of federal law. In December 2001, Judge Kessler granted the summary judgment motion made by the Conservation Law Foundation, finding that the agency had not complied with the overfishing and rebuilding provisions of the Magnuson-Stevens Act. Kessler found that the record did not show that the agency had properly reviewed the fishery and their management measures and disregarded the agency’s argument that the required reporting measures under federal law are “impractical and unnecessary.”


The agency admitted it had not complied with the overfishing and rebuilding provisions in Amendment 9 but claimed that “Framework 33,” a separate provision implementing fishing mortality targets, provided adequate protection for the groundfish fishery until a new amendment could be completed.4 Judge Kessler found for the plaintiffs because neither Framework 33 nor Amendment 9 met federal requirements.

Remedial Phase

Following the December 28, 2001 issuance of a Summary Judgment, the remedial phase began and seven additional parties intervened on behalf of the agency, along with many interested parties who wrote the court to express their concern about the impact of the court’s remedy. On February 15, 2002, a status conference was held between the parties where Judge Kessler, due to the far reaching impacts and complexity of the case and the relief it demanded, encouraged the two sides to enter into mediation.5 Because the fishing season was quickly approaching and the case had to be decided within serious time constraints, the parties entered into a five-day mediation and a “Settlement Agreement Among Certain Parties” was proposed and filed on April 16, 2002.

 In the meantime, in March of 2002, the agency filed its “2002 Working Group Report” regarding the status of New England groundfish. According to the report, many New England groundfish were not rebuilding fast enough after years of overfishing. This finding, according to the court, “changed the seascape” for groundfish management.

With the opening of fishing season lingering only eight days away, the court began the painstaking task of developing a remedy. In analyzing the evidence, briefs, and the technical information, Kessler stated “[m]uch of the blame for this situation can be laid at the feet of NMFS [National Marine Fisheries Service]. The very fact that this Court is in the unenviable position of having to decide such an important issue . . . reflects the failure of NMFS to comply with the statute in a timely fashion.6 

The court reexamined its mandate that the Government has a duty to enforce Amendment 9, claiming that “such course of action is now impossible. . . the scientific basis on which it relies has become invalid even though it may have been the best available . . . when the amendment was adopted7 and therefore, neither “the Settlement Agreement Among Certain Parties or the order the Court is now entering complies with Amendment 9.8 Thus, the court concluded it was suitable to use the settlement agreement as a starting point for the remedy, which provided that, until adoption of Amendment 13, significant restrictions would be imposed on days at sea, on the larger trawl vessels which account for much of the groundfish mortality, and on mesh sizes and gear to reduce bycatch and fish mortality. In addition, the court ordered significant area closures designed to protect the vulnerable Gulf of Maine cod and Georges Bank cod, an increase in the minimum size of cod that can be landed and possession limits. Finally, the court mandated increased observer coverage, the collection and analysis of timely and accurate fishing and bycatch information and a firm schedule for the adoption of Amendment 13.

 With the groundfish industry alarmed at the severe restrictions, the court granted a motion for reconsideration in May, noting that “the important changes made by the Court in the complex and carefully crafted Settlement Agreement. . . would produce unintended consequences” including the potential to further imperil the species and cause “grave economic and social hardship.9 The May decision vacated the April 26 order and called for an amended interim rule to be effective June 1, 2002, and an FMP amendment that complies with overfishing, rebuilding, and bycatch provisions of federal law to be submitted by August 22, 2003. The ultimate result was closing certain areas to groundfishing and cutting the numbers of days at sea.

Aftermath of the Decision

Federal Funding. Following the decision, members of Congress from the region called for federal assistance for fishermen harmed by the ruling.10 Congress appropriated funds for the cause; for example, the core of Maine’s groundfishing fleet is to receive $1.7 million designed to assist the industry in surviving the more stringent regulations. The Maine Department of Marine Resources plans to divide the money among over a hundred vessels that actively land groundfish in Maine.11 The payment, however, is a one-time payment and will not change the fact that the cut in days at sea will remain in place for the foreseeable future.

Scientific Uncertainty. In its May decision, the court also ordered the Secretary to make public the most current and reliable scientific information available to further the development of Amendment 13 and calculate the total allowable catch for the groundfish species. The scientific information that the Secretary, agencies, and Councils rely upon remains a source of dispute. In the fall of 2002, the NMFS announced that a net set inaccurately on a research vessel may have affected the agency’s estimation of the stocks’ health. The net was part of a trawl survey that provides stock assessment data to the agency and, in part, helps to determine if regulations are working to restore depleted fish stocks.12 As a result, Congressional members called for a delay in applying Kessler’s fishing restrictions in order to correct the faulty scientific data.13 

 NMFS 2003 Proposal. In the latest chapter of the New England groundfish story, the NMFS announced in January that Amendment 13, now scheduled to start in May 2004, will give fishermen until 2014 (instead of 2009) to rebuild stocks of New England groundfish. While the groundfishing industry applauds the proposal, the environmental community that originally sued federal regulators to win faster rebuilding, see the move as a way to “get around the law.”14


 The New England groundfish industry is not alone. Groundfish controversies are simmering in Alaska and on the west coast. With congressional members weighing in and the likelihood that future delays will be challenged in court, it may be many years before an appropriate remedy is fashioned and before a model for addressing fisheries management controversy is developed.



Endnotes
1.   Pub.L. No. 104-297, 110 Stat. 3559 (1996).
2.   16 U.S.C. §§ 1802 (28)-(29), 1853 (a)(10)-(11), 1854(e) (2002).
3.   The 12 species are: cod, haddock, yellowtail flounder, American plaice, witch flounder, winter flounder, redfish, white hake, pollock, windowpane flounder, ocean pout, and Atlantic halibut.
4.   209 F. Supp. 2d 1 (D. D.C. 2001).
5.   On April 8, 2002, due to the technical and scientific issues of the case, Kessler appointed a technical advisor to assist in deciding the remedy appropriate for the case. The technical advisor does not testify before the court but instead answers the court’s questions about terms, phrases, theories, and rationales.
6.   195 F. Supp. 2d 186, 191 at note 6 (D. D.C. 2002).
7.   Id. at 191.
8.   Id.
9.   211 F.Supp. 2d at 68.
10. See Susan Young, Federal Judge Reverses Groundfishing Decision, Bangor Daily News, May 24, 2002, A1.
11. See John Richardson, Maine Fishermen to Share $1.7 Million in Federal Assistance, Portland Press Herald, January 8, 2003, 9B.
12. See Doug Fraser, U.S. Lawmakers Call for Delay of New Fishing Regulations, Cape Cod Times, October 24, 2002.
13. Id.

14. See Kay Lazar, Fishermen Catch Break on Federal Restrictions, The Boston Herald, January 15, 2003, News 2.

 

Editor’s Note
The groundfish decisions can be found at:
• The December 28, 2001 decision granting summary judgment and finding that the federal agency failed to prevent overfishing and minimize bycatch is at 209 F. Supp. 2d 1 (D. D.C. 2001).

• The April 8, 2002 decision appointing a technical advisor to assist the court in deciding the case is at 203 F. Supp. 2d 27 (D. D.C. 2002).

• The April 26, 2002 decision granting plaintiff’s motion for summary judgment on the remedial issues and issuing an order with detailed provisions governing fishing in the multispecies New England groundfish until promulgation of a new amendment is at 195 F. Supp. 2d 186 (D. D.C. 2002).

• The May 23, 2002 decision granting reconsideration, vacating the April 26 decision, is at 211 F. Supp. 2d 55 (D. D.C. 2002).

 
   
   
   
   
   
   
   
   



Phone (662) 915-7775 • Fax (662) 915-5267 • 256 Kinard Hall, Wing E, University, MS 38677-1848

Sitemap • Please report any broken links/problems to the Webmaster

University of Mississippi